- 204 Canadian Bay Road Mount Eliza 3930
Schools Upgrade Fund
Start
Q2 2024Planning
Design
Construction
Finish
Q2 2027
The above dates are forecast only and subject to change.
About the project
We are refurbishing the science wing to provide new science classrooms complete with chemical store and staff work/preparation areas. Technology areas created nearby will provide learning spaces with breakout and informal learning zones.
Funding
In the Australian Government Schools Upgrade Fund – Round 1, the school received $7.3 million.
Funding type
- Australian Government Schools Upgrade Fund
Minor Capital Works Fund
Start
Q2 2022Planning
Design
Construction
Finish
Q3 2024
The above dates are forecast only and subject to change.
About the project
We refurbished the student toilet facilities in the school's canteen and well-being areas to improve amenity, cleanliness and hygiene. This work was supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.
Funding
In the 2022-23 State Budget the project received $499,127 from the Minor Capital Works Fund.
Funding type
- Minor Capital Works Fund